Chicago / Permit application status

8000 S Lake Shore Dr

New Construction · Direct Developer Services

Official application status ↗
Latest checked statusIssued / ready date listed
Application startedApr 17, 2026
Issued / ready dateOct 7, 2026

The portal's issue date usually means ready to issue subject to fees. A blank issue date does not establish an active construction proposal: administrative changes, denied reviews and incomplete applications can also appear. Construction progress and open bids are separate facts.

Work described by the source

Building work

Work described
Building work
Official application number
Not supplied in this public address view
First observed here
Oct 6, 2026, 11:43 a.m. ET
Facts checked here
Nov 2, 2026, 11:03 a.m. ET
City display timestamp
Information shown is current as of Monday, November 02, 9:00 AM.

Related planning proposals

Advocate New Trinity Hospital ↗ · As of Oct 6, 2026

These links reflect the proposed work and source documents at the dates shown. Separate records and phases may concern different projects.

Latest checked reviews and holds

Administrative Hold (Department of Planning and Development)

Hold Released

2026-10-06
City Debt (Revenue) Review

Approved

2026-05-15
Developer Services Plan Review

Approved

2026-10-07
FINAL DATA REVIEW

Approved

2026-10-07
GEOTECH REVIEW

Approved

2026-09-17
LANDSCAPE REVIEW (ZONING)

Approved

2026-10-05
PLANNING REVIEW

Approved

2026-10-06
PRELIMINARY INTAKE REVIEW

Approved

2026-04-17
ZONING REVIEW

Waived

Date not supplied

Observed source changes

These observations begin with CivicBuilds' first check. They do not reconstruct earlier statuses.

New Construction · Issue / ready date: 2026-10-07

New Construction · Issue / ready date: Not listed